Moorlands Park Project

Moorlands Park

 

Status and Schedule:

  • Public review of Proposed Park Design: Open House Wednesday, October 5, 2016 at Moorlands Elementary.
  • City Council approved the updated Park Master Plan on November 21, 2016.
  • Permit application and review: November 2016 to March 2017.
  • Construction bid awarded: June 12, 2017
  • Park is closed to the public during construction: late November 2017
  • Construction Start: June 27, 2017
  • Construction Completion: late November 2017 (anticipated)
  • Park open to public: December, 2017
  • Ballfield open to public use: January 2019

 

Project Description:

The Moorlands Park renovation will construct park improvements, including ballfield renovation, new picnic shelter, perimeter path and play area upgrades.

 

Background:

Moorlands Park was first established as a neighborhood park in the 1940s. It was transferred to the city from King County Parks in 2002 following Kenmore’s incorporation. The City of Kenmore prepared a park master plan in 2006. 

 

Budget: 

Total project budget is $1,980,000. The City received funding assistance of $637,520 from the Washington State Recreation and Conservation Office.

 

Contact: 

Ann Stanton
Parks Project Manager
astanton@kenmorewa.gov
425 398-8900

Last updated: Fri, 06/23/2017 - 2:06pm